TEP-109
200 MW generation in Pima, AZ · In queue since December 2021 · Proposed COD May 2024
200 MW
Capacity
1
Components
Other
4y 5m
In Queue
—
IA Status
COD target: 2024
Total Duration
2y 5m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-31
TEP-109 is a proposed 200 MW generation project located in Pima County, Arizona. The project, developed by TEP (Tucson Electric Power Company), is listed in the CAISO interconnection queue as of December 21, 2021, with a proposed commercial operation date of May 31, 2024. The project's point of interconnection is the Vail 138kV Substation.
The project is categorized as "Other" technology, with 200 MW of capacity attributed to this technology type. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Pima
Grid Region
Mountain West
Market
—
Developer
TEP
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
Vail 138kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TEP-109