TEP-115
100 MW generation in Pima, AZ · In queue since March 2022 · Proposed COD October 2025
100 MW
Capacity
1
Components
Other
4y 2m
In Queue
—
IA Status
COD target: 2025
Total Duration
3y 7m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-31
TEP-115 is a proposed 100 MW generation project located in Pima County, Arizona. The project, under development by Tucson Electric Power Company (TEP), consists of an "Other" technology resource. It is interconnected to the DMP 138kV point of interconnection.
The project is listed in the Tucson Electric Power queue (TEP-115) as of March 28, 2022, with a proposed commercial operation date of October 31, 2025. The project's status is listed as "active".
Generated from interconnection queue and public data sources
State
AZ
County
Pima
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
DMP 138kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.