TEP-116
100 MW generation in Pima, AZ · In queue since March 2022 · Proposed COD December 2025
100 MW
Capacity
1
Components
Other
4y 2m
In Queue
—
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
TEP-116 is a proposed 100 MW generation project in Pima County, Arizona. The project, located in the West region, is being developed by Tucson Electric Power Company (TEP). The technology is listed as "Other."
The project is currently active in the Tucson Electric Power Company interconnection queue, with a queue entry date of March 29, 2022, and a proposed commercial operation date of December 1, 2025. The point of interconnection is the Cisne 138kV substation.
Generated from interconnection queue and public data sources
State
AZ
County
Pima
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
Cisne 138kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TEP-116