TEP-120
200 MW generation in Cochise, AZ · In queue since May 2022 · Proposed COD December 2025
200 MW
Capacity
1
Components
Wind
4 years
In Queue
—
IA Status
COD target: 2025
Total Duration
3y 7m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
The proposed TEP-120 project is a 200 MW wind generation facility located in Cochise County, Arizona. The project is sponsored by Tucson Electric Power Company (TEP). It consists of 200 MW of wind generation capacity.
The project is currently active in the Tucson Electric Power queue, with an interconnection queue entry date of May 2, 2022, and a proposed commercial operation date of December 31, 2025. The point of interconnection is the Sprinerville-Vail 345kV Transmission Line.
Generated from interconnection queue and public data sources
State
AZ
County
Cochise
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
Sprinerville-Vail 345kV Transmission Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TEP-120