Project TEP-124 — Project Summary

Queue ID
TEP-124
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status

TEP-124

TEP-124BetaActiveSolarBatteryTEPLBNL

300 MW hybrid in Pinal, AZ · In queue since June 2022 · Proposed COD December 2025

300 MW

Capacity

1

Components

Solar

3y 11m

In Queue

IA Status

COD target: 2025

Interconnection

Total Duration

3y 6m

Schedule

4 months past proposed COD

Pre-Study0%
Queue EntryJun 16, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

About

The proposed TEP-124 project is a 300 MW solar and battery hybrid development in Pinal County, Arizona. The project consists of 300 MW of solar generation, and is located in the western region of the US. Tucson Electric Power Company (TEP) is the utility associated with the project.

TEP-124 is currently in the Tucson Electric Power interconnection queue with an entry date of June 16, 2022. The proposed commercial operation date is December 31, 2025. The point of interconnection is the Pinal West 345kV Substation.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Pinal

Grid Region

Mountain West

Market

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Service Type

Point of Interconnection

Pinal West 345kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.