Project TEP-143 — Project Summary

Queue ID
TEP-143
Capacity
200 MW
Technology
Battery
Status
active
Location
Pima, AZ
Region
West
Developer
IA Status

TEP-143

TEP-143BetaActiveBatteryTEPLBNL

200 MW storage in Pima, AZ · In queue since November 2022 · Proposed COD December 2025

200 MW

Capacity

1

Components

Battery

3y 6m

In Queue

IA Status

COD target: 2025

Interconnection

Total Duration

3y 1m

Schedule

4 months past proposed COD

Pre-Study0%
Queue EntryNov 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

About

TEP-143 is a proposed 200 MW battery storage project located in Pima County, Arizona. The project is being developed by Tucson Electric Power Company (TEP) and interconnected to the Vail 138kV Substation. It entered the transmission interconnection queue for the regional ISO/RTO on November 15, 2022, with a proposed commercial operation date of December 31, 2025.

The project consists entirely of battery storage, with a total capacity of 200 MW. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Pima

Grid Region

Mountain West

Market

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Service Type

Point of Interconnection

Vail 138kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project TEP-143