TEP-165
100 MW hybrid in Pima, AZ · In queue since September 2023 · Proposed COD December 2028
100 MW
Capacity
1
Components
Solar
2y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
TEP-165 is a proposed 100 MW hybrid solar and battery project located in Pima County, Arizona. The development project consists of 100 MW of solar generation capacity. It is listed in the Tucson Electric Power Company interconnection queue (TEP-165) with an entry date of September 29, 2023, and a proposed commercial operation date of December 1, 2028.
The point of interconnection for the project is the Sonoran 138kV Substation. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Pima
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
Sonoran 138kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TEP-165