TEP-174
800 MW generation in Pima, AZ · In queue since June 2024 · Proposed COD December 2027
800 MW
Capacity
1
Components
Gas
1y 11m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
TEP-174 is a proposed 800 MW gas-fired generation project located in Pima County, Arizona. The project is being developed by Tucson Electric Power Company (TEP). It entered the CAISO interconnection queue on June 14, 2024, with a proposed commercial operation date of December 31, 2027. The point of interconnection is the Irvington 138kV Substation.
The project consists of 800 MW of gas-fired generation capacity. It is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Pima
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
Irvington 138kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TEP-174