TEP-62
300 MW generation in Pima, AZ · In queue since September 2018 · Proposed COD May 2023
300 MW
Capacity
1
Components
Other
7y 8m
In Queue
IA Pending
IA Status
COD target: 2023
Total Duration
4y 8m
Schedule
37 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-05-01
The TEP-62 development project is a proposed 300 MW generation project located in Pima County, Arizona. The project, under development by Tucson Electric Power Company (TEP), utilizes an unspecified "Other" technology. It is interconnected to the Pinal West 345 kV point of interconnection.
The project is currently active in the WestConnect interconnection queue as entry TEP-62, with a queue entry date of September 27, 2018. The proposed commercial operation date is May 1, 2023, and the interconnection agreement status is currently listed as "IA Pending".
Generated from interconnection queue and public data sources
State
AZ
County
Pima
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
Pinal West 345 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.