TEP-72
80 MW generation in Pima, AZ · In queue since January 2020 · Proposed COD November 2022
80 MW
Capacity
1
Components
Other
6y 4m
In Queue
IA Pending
IA Status
COD target: 2022
Total Duration
2y 10m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-11-20
TEP-72 is a proposed 80 MW generation project located in Pima County, Arizona. The project, listed in the West region interconnection queue of Tucson Electric Power Company (TEP), consists of 80 MW of unspecified "Other" technology. The queue entry date is January 24, 2020, with a proposed commercial operation date of November 20, 2022. The interconnection agreement (IA) status is currently listed as "IA Pending".
The development project is sponsored by TEP. The point of interconnection (POI) is the Tortolita 138kV substation. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Pima
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
Tortolita 138kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TEP-72