TEP-86
250 MW generation in Apache, AZ · In queue since December 2020 · Proposed COD December 2023
250 MW
Capacity
1
Components
Other
5y 5m
In Queue
IA Pending
IA Status
COD target: 2023
Total Duration
3 years
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
TEP-86 is a proposed 250 MW generation project located in Apache County, Arizona. The project, developed by Tucson Electric Power Company (TEP), utilizes an "Other" technology type. It is interconnected to the Springerville 345kV Substation.
The project is currently in the Tucson Electric Power Company interconnection queue (TEP-86) with an entry date of December 16, 2020. Its proposed commercial operation date is December 1, 2023, and the interconnection agreement is currently pending. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
AZ
County
Apache
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
Springerville 345kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.