TEP-93
400 MW generation in Apache, AZ · In queue since April 2021 · Proposed COD December 2021
400 MW
Capacity
1
Components
Other
5y 1m
In Queue
IA Pending
IA Status
COD target: 2021
Total Duration
8 months
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
The proposed project TEP-93 is a 400 MW generation project located in Apache County, Arizona. The project, which utilizes an unspecified "Other" technology, is being developed by Tucson Electric Power Company (TEP). It is interconnected to the Springerville-Mckinley 345kV Transmission Line.
The project is currently in the West interconnection queue, having entered the queue on April 26, 2021. The proposed commercial operation date is December 31, 2021, and the Interconnection Agreement (IA) is currently pending.
Generated from interconnection queue and public data sources
State
AZ
County
Apache
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
Springerville-Mckinley 345kV Transmission Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.