TEP-95
250 MW generation in Apache, AZ · In queue since June 2021 · Proposed COD December 2024
250 MW
Capacity
1
Components
Other
4y 11m
In Queue
—
IA Status
COD target: 2024
Total Duration
3y 6m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
TEP-95 is a proposed 250 MW generation project located in Apache County, Arizona. The project, under development by Tucson Electric Power Company (TEP), is categorized as "Other" technology. It consists of a single 250 MW component of "Other" type.
The project is currently active in the Tucson Electric Power Company interconnection queue, with an entry date of June 17, 2021. The proposed commercial operation date is December 31, 2024. The point of interconnection is the Coronado 345kV Substation.
Generated from interconnection queue and public data sources
State
AZ
County
Apache
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
Coronado 345kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.