TEP-98
241 MW generation in Pinal, AZ · In queue since September 2021 · Proposed COD December 2025
241 MW
Capacity
1
Components
Other
4y 8m
In Queue
—
IA Status
COD target: 2025
Total Duration
4y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
TEP-98 is a proposed 241 MW generation project located in Pinal County, Arizona. The project, listed in the West region interconnection queue of Tucson Electric Power Company (TEP), consists of 241 MW of unspecified "Other" technology. The queue entry date is September 28, 2021, with a proposed commercial operation date of December 31, 2025.
The point of interconnection is the Pinal West - West Wing 345kV substation. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
Pinal West - West Wing 345kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.