Project TEP-98 — Project Summary

Queue ID
TEP-98
Capacity
241 MW
Technology
Other
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status

TEP-98

TEP-98BetaActiveOtherTEPLBNL

241 MW generation in Pinal, AZ · In queue since September 2021 · Proposed COD December 2025

241 MW

Capacity

1

Components

Other

4y 8m

In Queue

IA Status

COD target: 2025

Interconnection

Total Duration

4y 3m

Schedule

4 months past proposed COD

Pre-Study0%
Queue EntrySep 28, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

About

TEP-98 is a proposed 241 MW generation project located in Pinal County, Arizona. The project, listed in the West region interconnection queue of Tucson Electric Power Company (TEP), consists of 241 MW of unspecified "Other" technology. The queue entry date is September 28, 2021, with a proposed commercial operation date of December 31, 2025.

The point of interconnection is the Pinal West - West Wing 345kV substation. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Pinal

Grid Region

Mountain West

Market

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Service Type

Point of Interconnection

Pinal West - West Wing 345kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.