TSGT-GI-DISIS-2021-01
120 MW generation in Harding, NM · In queue since April 2021
120 MW
Capacity
1
Components
Solar
5y 1m
In Queue
IA Executed
IA Status
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Commercial operation date not yet determined
The proposed TSGT-GI-DISIS-2021-01 project is a 120 MW solar generation facility located in Harding County, New Mexico. The developer is Tri-State Generation and Transmission Association (TSGT). This project is actively listed in the Tri-State Generation and Transmission Association interconnection queue with an entry date of April 15, 2021. An Interconnection Agreement (IA) has been executed for the project.
The project is located in the western region of the United States and will interconnect at the Gladstone-Bravo Dome West 115kV Line.
Generated from interconnection queue and public data sources
State
NM
County
Harding
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Gladstone-Bravo Dome West 115kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-DISIS-2021-01