TSGT-GI-DISIS-2021-06
140 MW generation in Montezuma, CO · In queue since May 2021
140 MW
Capacity
1
Components
Solar
5 years
In Queue
IA Executed
IA Status
Total Duration
5 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Commercial operation date not yet determined
The proposed solar project TSGT-GI-DISIS-2021-06 is a 140 MW solar generation facility located in Montezuma County, Colorado. The project is being developed by Tri-State Generation and Transmission Association (TSGT). It is currently active in the DISIS queue of the Transmission System Group of the West region, having entered the queue on May 27, 2021. The interconnection agreement (IA) for the project has been executed.
The point of interconnection (POI) for the project is the Main Switch 115kV Substation. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
CO
County
Montezuma
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Main Switch 115kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN