TSGT-GI-DISIS-2021-11
300 MW hybrid in Las Animas, CO · In queue since May 2021
300 MW
Capacity
2
Components
Solar + Battery
5 years
In Queue
Suspended
IA Status
Total Duration
5 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
TSGT-GI-DISIS-2021-11 is a proposed 300 MW hybrid Solar+Battery project located in Las Animas County, Colorado. The project, developed by Tri-State Generation and Transmission Association (TSGT), consists of a 200 MW solar array coupled with a 100 MW battery energy storage system. It is interconnected to the Walsenburg-Gladstone 230kV Line.
The project entered the Tri-State Generation and Transmission Association interconnection queue on May 28, 2021. Its interconnection status is currently listed as "suspended," and its Interconnection Agreement (IA) status is also "suspended." The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CO
County
Las Animas
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Walsenburg-Gladstone 230kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-DISIS-2021-11