Project TSGT-GI-DISIS-2022-44 — Project Summary

Queue ID
TSGT-GI-DISIS-2022-44
Capacity
299 MW
Technology
Solar+Battery
Status
active
Location
Moffat, CO
Region
West
Developer
IA Status
IA Executed

TSGT-GI-DISIS-2022-44

TSGT-GI-DISIS-2022-44BetaActiveSolarBatteryTSGTLBNL

299 MW hybrid in Moffat, CO · In queue since May 2022

299 MW

Capacity

2

Components

Solar + Battery

4 years

In Queue

IA Executed

IA Status

Interconnection

Total Duration

4 years

Construction75%
Queue EntryMay 31, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Commercial operation date not yet determined

Technology
Solar199 MW · 67%
Battery100 MW · 33%
About

The proposed TSGT-GI-DISIS-2022-44 project is a 299 MW hybrid solar and battery energy storage system located in Moffat County, Colorado. The project, developed by Tri-State Generation and Transmission Association (TSGT), consists of a 199 MW solar array coupled with a 100 MW battery.

The project is currently active in the Tri-State Generation and Transmission Association interconnection queue, having entered the queue on May 31, 2022. The interconnection agreement has been executed. The point of interconnection is the Craig 345kV Substation.

Generated from interconnection queue and public data sources

Project Details

State

CO

County

Moffat

Grid Region

Mountain West

Market

Developer

Utility

Tri-State Generation and Transmission Association

Entity

TSGT

Service Type

Point of Interconnection

Craig 345kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project TSGT-GI-DISIS-2022-44