TSGT-GI-TC-2021-03
110 MW generation in Dolores, CO · In queue since March 2021
110 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
Signed Jun 2024
Queue → IA
3y 3m
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Commercial operation date not yet determined
The proposed TSGT-GI-TC-2021-03 project is a 110 MW solar generation facility located in Dolores County, Colorado. The project is being developed by Tri-State Generation and Transmission Association (TSGT). It is currently active in the utility's interconnection queue, having entered on March 15, 2021.
The project has an executed Interconnection Agreement (IA), dated June 14, 2024. The point of interconnection (POI) for the project is Cahone. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CO
County
Dolores
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Cahone
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-TC-2021-03