TSGT-GI-TC-2021-04
40 MW generation in Las Animas, CO · In queue since March 2021
40 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
Signed Sep 2024
Queue → IA
3y 6m
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Commercial operation date not yet determined
The proposed solar generation project TSGT-GI-TC-2021-04 is a 40 MW development in Las Animas County, Colorado. The project, under the utility Tri-State Generation and Transmission Association (TSGT), consists of 40 MW of solar photovoltaic generation. It is interconnected to the Walsenburg-Gladstone 230 kV Line.
The project is currently active in the transmission interconnection queue for TSGT, with an original queue entry date of March 15, 2021. The Interconnection Agreement (IA) for the project has been executed as of September 1, 2024.
Generated from interconnection queue and public data sources
State
CO
County
Las Animas
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Walsenburg-Gladstone 230 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.