TSGT-GI-TC-2021-05
200 MW generation in Mckinley, NM · In queue since March 2021
200 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
2y 8m
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Commercial operation date not yet determined
The proposed TSGT-GI-TC-2021-05 project is a 200 MW solar generation facility located in McKinley County, New Mexico. The project is being developed within the Tri-State Generation and Transmission Association (TSGT) service area. It consists of 200 MW of solar photovoltaic generation.
The project is listed in the TSGT interconnection queue with an entry date of March 15, 2021. The interconnection agreement (IA) for the project was executed on November 1, 2023. The point of interconnection (POI) for the project is the PEGS 230kV Station. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NM
County
Mckinley
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
PEGS 230kV Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-TC-2021-05