TSGT-GI-TC-2021-07
80 MW generation in Delta, CO · In queue since March 2021
80 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
Signed May 2024
Queue → IA
3y 2m
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Commercial operation date not yet determined
The proposed TSGT-GI-TC-2021-07 project is an 80 MW solar generation project located in Delta County, Colorado. The developer is Tri-State Generation and Transmission Association (TSGT). It is interconnected to the Garnet Mesa 115kV Substation.
The project is in the Tri-State Generation and Transmission Association interconnection queue, with an original queue entry date of March 15, 2021. The Interconnection Agreement (IA) was executed on May 1, 2024, and the project is currently listed as active.
Generated from interconnection queue and public data sources
State
CO
County
Delta
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Garnet Mesa 115kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.