TSGT-GI-TC-2024-01
150 MW hybrid in Lincoln, CO · In queue since April 2024 · Proposed COD June 2027
150 MW
Capacity
1
Components
Solar
2y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-30
TSGT-GI-TC-2024-01 is a proposed 150 MW hybrid solar and battery project located in Lincoln County, Colorado. The development project, with Tri-State Generation and Transmission Association (TSGT) as the utility, consists of 150 MW of solar capacity.
The project is currently active in the TSGT interconnection queue, having entered the queue on April 25, 2024, with a proposed commercial operation date of June 30, 2027. The interconnection agreement status is listed as "In Progress (unknown study)" and the point of interconnection is the Lincoln 230kV Substation.
Generated from interconnection queue and public data sources
State
CO
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Lincoln 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.