TSGT-GI-TC-2024-03
160 MW generation in Platte, WY · In queue since May 2023 · Proposed COD December 2028
160 MW
Capacity
1
Components
Solar
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-28
TSGT-GI-TC-2024-03 is a proposed 160 MW solar generation project located in Platte County, Wyoming. The project is being developed by Tri-State Generation and Transmission Association (TSGT). It is currently active in the utility's interconnection queue, with an entry date of May 8, 2023, and a proposed commercial operation date of December 28, 2028. The point of interconnection is the Monolith 115 kV Substation.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". Recent news coverage indicates interest in renewable energy projects in the Western region.
Generated from interconnection queue and public data sources
State
WY
County
Platte
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Monolith 115 kVSubstation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.