TSGT-GI-TC-2024-07
199 MW generation in Cheyenne, CO · In queue since May 2023 · Proposed COD December 2028
199 MW
Capacity
1
Components
Solar
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
The proposed project, identified as TSGT-GI-TC-2024-07, is a 199 MW solar generation project located in Cheyenne County, Colorado. The developer is Tri-State Generation and Transmission Association (TSGT). It is interconnected to the Burlington - Lamar 230 kV Line.
The project is currently active in the utility's interconnection queue, with an entry date of May 22, 2023. The proposed commercial operation date is December 31, 2028. The interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
CO
County
Cheyenne
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Burlington - Lamar 230 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-TC-2024-07