TSGT-GI-TC-2024-08
150 MW generation in Kit Carson, CO · In queue since May 2023 · Proposed COD December 2028
150 MW
Capacity
1
Components
Wind
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-27
The proposed wind generation project, identified as TSGT-GI-TC-2024-08, is a 150 MW development in Kit Carson County, Colorado. The project, sponsored by Tri-State Generation and Transmission Association (TSGT), entered the transmission queue on May 26, 2023, and has a proposed commercial operation date of December 27, 2028. The point of interconnection is the Burlington 230kV Substation.
The project's interconnection agreement status is currently listed as "In Progress (unknown study)". Recent news coverage has discussed the project's potential impact on the region's energy infrastructure.
Generated from interconnection queue and public data sources
State
CO
County
Kit Carson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Burlington 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-TC-2024-08