TSGT-GI-TC-2024-10
199 MW generation in Kit Carson, CO · In queue since May 2024 · Proposed COD December 2028
199 MW
Capacity
1
Components
Solar
2 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-29
The proposed solar generation project, identified as TSGT-GI-TC-2024-10, is a 199 MW solar energy development in Kit Carson County, Colorado. The project is sponsored by Tri-State Generation and Transmission Association (TSGT). It is currently listed as active in the transmission interconnection queue for TSGT, with an interconnection queue entry date of May 23, 2024, and a proposed commercial operation date of December 29, 2028.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Burlington 230kV Substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CO
County
Kit Carson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Burlington 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-TC-2024-10