TSGT-GI-TC-2024-12
170 MW generation in Yuma, CO · In queue since May 2024 · Proposed COD October 2027
170 MW
Capacity
1
Components
Wind
2 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-31
TSGT-GI-TC-2024-12 is a proposed 170 MW wind generation project located in Yuma County, Colorado. The project, developed by Tri-State Generation and Transmission Association (TSGT), is interconnected to the Burlington-Wray 230kV Line. It is currently listed as active in the transmission interconnection queue for TSGT, with a queue entry date of May 21, 2024.
The proposed commercial operation date (COD) for the project is October 31, 2027. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The project has appeared in recent news coverage regarding renewable energy development in the Western United States.
Generated from interconnection queue and public data sources
State
CO
County
Yuma
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Burlington-Wray 230kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-TC-2024-12