TSGT-GI-TC-2024-13
250 MW hybrid in Routt, CO · In queue since May 2024 · Proposed COD December 2027
250 MW
Capacity
1
Components
Solar
2 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The proposed project TSGT-GI-TC-2024-13 is a 250 MW hybrid solar and battery energy storage development in Routt County, Colorado. The project, located in the Western region, is being proposed by Tri-State Generation and Transmission Association (TSGT). It consists of 250 MW of solar generation, coupled with an unspecified amount of battery storage.
The project is currently active in the TSGT interconnection queue, with an initial queue entry date of May 23, 2024. The developer anticipates a commercial operation date of December 31, 2027. The interconnection agreement is currently listed as "In Progress (unknown study)". The point of interconnection is the Craig-Hayden West 230kV Line.
Generated from interconnection queue and public data sources
State
CO
County
Routt
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Craig-Hayden West 230kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-TC-2024-13