TSGT-GI-TC-2024-16
400 MW generation in Laramie, WY · In queue since May 2023 · Proposed COD December 2027
400 MW
Capacity
1
Components
Wind
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
TSGT-GI-TC-2024-16 is a proposed 400 MW wind generation project located in Laramie County, Wyoming. The project is being developed by Tri-State Generation and Transmission Association (TSGT). It entered the transmission interconnection queue on May 16, 2023, with a proposed commercial operation date of December 31, 2027.
The project is currently listed as "active" in the interconnection queue, and its Interconnection Agreement (IA) status is "In Progress (unknown study)". The point of interconnection (POI) is the Ault-Laramie River Station 345kV Line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
WY
County
Laramie
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Ault-Laramie River Station 345kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-TC-2024-16