TSGT-GI-TC-2024-17
225 MW generation in Kit Carson, CO · In queue since May 2024 · Proposed COD January 2030
225 MW
Capacity
1
Components
Solar
2 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
5y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-01-01
The proposed TSGT-GI-TC-2024-17 project is a 225 MW solar generation facility located in Kit Carson County, Colorado. The project is being developed within the Tri-State Generation and Transmission Association (TSGT) service area. It entered the transmission interconnection queue on May 29, 2024, with a proposed commercial operation date of January 1, 2030.
The interconnection agreement (IA) for the project is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Burlington-Wray 230kV Line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CO
County
Kit Carson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Burlington-Wray 230kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-TC-2024-17