TSGT-GI-TC-2024-19
100 MW storage in Montrose, CO · In queue since May 2024 · Proposed COD May 2026
100 MW
Capacity
1
Components
Battery
2 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
2 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-31
TSGT-GI-TC-2024-19 is a proposed 100 MW battery storage project located in Montrose County, Colorado. The project is being developed by Tri-State Generation and Transmission Association (TSGT). It consists of a single 100 MW battery component.
The project is currently active in the Tri-State Generation and Transmission Association interconnection queue, with an entry date of May 7, 2024. The proposed commercial operation date is May 31, 2026. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Montrose 115kV Substation.
Generated from interconnection queue and public data sources
State
CO
County
Montrose
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Montrose 115kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.