TSGT-GI-TC-2024-20
250 MW generation in Lincoln, CO · In queue since May 2024 · Proposed COD July 2027
250 MW
Capacity
1
Components
Solar
2 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
The proposed TSGT-GI-TC-2024-20 project is a 250 MW solar generation facility located in Lincoln County, Colorado. The developer is Tri-State Generation and Transmission Association (TSGT). The project entered the transmission interconnection queue on May 29, 2024, with a proposed commercial operation date of July 1, 2027.
The project is actively listed in the interconnection queue and its interconnection agreement (IA) status is "In Progress (unknown study)". The point of interconnection (POI) is the Big Sandy 230kV Substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CO
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Big Sandy 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-TC-2024-20