TSGT-GI-TC-2024-21
125 MW hybrid in Montezuma, CO · In queue since May 2024 · Proposed COD December 2028
125 MW
Capacity
1
Components
Solar
2 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
TSGT-GI-TC-2024-21 is a proposed 125 MW hybrid solar and battery energy storage project located in Montezuma County, Colorado. The development project, located in the Western region, is being proposed by Tri-State Generation and Transmission Association (TSGT). The project consists of 125 MW of solar capacity.
The project is currently active in the TSGT interconnection queue, having entered the queue on May 24, 2024, with a proposed commercial operation date of December 31, 2028. The interconnection agreement is currently listed as "In Progress (unknown study)". The point of interconnection is the East Cortez 115kV Substation.
Generated from interconnection queue and public data sources
State
CO
County
Montezuma
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
East Cortez 115kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-TC-2024-21