TSGT-GI-TC-2024-22
140 MW generation in Weld, CO · In queue since May 2024 · Proposed COD March 2028
140 MW
Capacity
1
Components
Solar
2 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
TSGT-GI-TC-2024-22 is a proposed solar generation project with a total capacity of 140 MW. The project is located in Weld County, Colorado, within the service territory of Tri-State Generation and Transmission Association (TSGT).
The project is currently active in the transmission interconnection queue of TSGT, having entered the queue on May 23, 2024. The proposed commercial operation date is March 1, 2028. The interconnection agreement is currently listed as "In Progress (unknown study)". The point of interconnection is the Lloyd Sisson 115 kV Substation.
Generated from interconnection queue and public data sources
State
CO
County
Weld
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Lloyd Sisson 115 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.