TSGT-GI-TC-2024-24
199 MW hybrid in Bent, CO · In queue since May 2023 · Proposed COD May 2029
199 MW
Capacity
1
Components
Solar
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-01
TSGT-GI-TC-2024-24 is a proposed 199 MW hybrid solar and battery project located in Bent County, Colorado. The project, developed by Tri-State Generation and Transmission Association (TSGT), consists of 199 MW of solar capacity. It is currently listed as active in the TSGT interconnection queue, with an entry date of May 31, 2023, and a proposed commercial operation date of May 1, 2029.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Boone-Lamar 230 kV Line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CO
County
Bent
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Boone -Lamar 230 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-TC-2024-24