TSGT-GI-TC-2024-27
298 MW generation in Sherman, KS · In queue since May 2023 · Proposed COD December 2028
298 MW
Capacity
1
Components
Wind
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
The proposed TSGT-GI-TC-2024-27 project is a 298 MW wind generation facility located in Sherman County, Kansas. The project is being developed by Tri-State Generation and Transmission Association (TSGT). It is currently active in the Southwest Power Pool (SPP) interconnection queue, with an entry date of May 30, 2023, and a proposed commercial operation date of December 31, 2028. The point of interconnection is the Burlington 230 kV Substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)". Recent news coverage indicates public interest in the development.
Generated from interconnection queue and public data sources
State
KS
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Burlington 230 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-GI-TC-2024-27