TSGT-GI-TC-2024-28
222.3 MW generation in Weld, CO · In queue since May 2023 · Proposed COD December 2027
222.3 MW
Capacity
1
Components
Solar
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
TSGT-GI-TC-2024-28 is a proposed solar generation project located in Weld County, Colorado, with a total capacity of 222.3 MW. The project is being developed by Tri-State Generation and Transmission Association (TSGT). It is currently active in the transmission interconnection queue of an unknown ISO/RTO, having entered the queue on May 31, 2023. The proposed commercial operation date is December 31, 2027.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Lloyd Sisson 115 kV Substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CO
County
Weld
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Lloyd Sisson 115 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.