TSGT-TI-18-0809
100 MW generation in Las Animas, CO · In queue since August 2018
100 MW
Capacity
1
Components
Solar
7y 9m
In Queue
IA Executed
IA Status
Signed Jun 2024
Queue → IA
5y 10m
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Commercial operation date not yet determined
The proposed project TSGT-TI-18-0809 is a 100 MW solar generation project located in Las Animas County, Colorado. The developer is Tri-State Generation and Transmission Association (TSGT). It is interconnected to the Walsenburg-Gladstone 230 kV Line.
The project is in the Tri-State Generation and Transmission Association interconnection queue with a queue entry date of August 9, 2018. The interconnection agreement was executed on June 1, 2024.
Generated from interconnection queue and public data sources
State
CO
County
Las Animas
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
—
Point of Interconnection
Walsenburg-Gladstone 230 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TSGT-TI-18-0809