TVA-254
155 MW generation in Limestone, AL · In queue since August 2014 · Proposed COD April 2018
155 MW
Capacity
1
Components
Nuclear
11y 9m
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
3y 8m
Schedule
98 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 60–120 months
Proposed COD: 2018-04-30
TVA-254 is a proposed nuclear generation project with a total capacity of 155 MW located in Limestone County, Alabama. The project is sponsored by the Tennessee Valley Authority (TVA) and interconnected to the BFN 500-kV Substation.
The project is listed in the TVA interconnection queue with an entry date of August 15, 2014. The proposed commercial operation date (COD) is April 30, 2018, and the Interconnection Agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
AL
County
Limestone
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
BFN 500-kV Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-254