TVA-299
67 MW generation in Lake, TN · In queue since July 2016 · Proposed COD March 2020
67 MW
Capacity
1
Components
Solar
9y 10m
In Queue
IA Executed
IA Status
COD target: 2020
Total Duration
3y 8m
Schedule
75 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2020-03-01
TVA-299 is a proposed 67 MW solar generation project located in Lake County, Tennessee. The development project is in the Tennessee Valley Authority (TVA) interconnection queue, with an original queue entry date of July 28, 2016. The proposed commercial operation date is March 1, 2020, and the interconnection agreement has been executed.
The project, sponsored by TVA, consists of 67 MW of solar photovoltaic generation. The point of interconnection is the Highway 412-New Tiptonville 161-kV transmission line.
Generated from interconnection queue and public data sources
State
TN
County
Lake
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Highway 412-New Tiptonville 161-kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-299