TVA-304
14 MW generation in Shelby, TN · In queue since November 2016 · Proposed COD March 2018
14 MW
Capacity
1
Components
Gas
9y 6m
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
1y 4m
Schedule
100 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2018-03-01
TVA-304 is a proposed 14 MW gas-fired generation project located in Shelby County, Tennessee. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of November 21, 2016, and a proposed commercial operation date of March 1, 2018. The interconnection agreement for the project has been executed. The point of interconnection is the Allen 161-kV Substation.
The development project is composed of 14 MW of gas-fired generation capacity. The project is sponsored by TVA.
Generated from interconnection queue and public data sources
State
TN
County
Shelby
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Allen 161-kV Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-304