TVA-321
11 MW generation in Marion, TN · In queue since August 2017 · Proposed COD January 2021
11 MW
Capacity
1
Components
Hydro
8y 9m
In Queue
Facility Study
IA Status
COD target: 2021
Total Duration
3y 5m
Schedule
64 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-01-15
The TVA-321 development project is a proposed 11 MW hydroelectric generation facility located in Marion County, Tennessee. The project, under the purview of the Tennessee Valley Authority (TVA), entered the TVA interconnection queue on August 4, 2017. Its proposed commercial operation date is January 15, 2021, and its interconnection status is currently in the Facility Study phase. The point of interconnection is the Raccoon Mountain 161-kV Substation.
This proposed project has appeared in recent news coverage regarding TVA's generation portfolio.
Generated from interconnection queue and public data sources
State
TN
County
Marion
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Raccoon Mountain 161-kV Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-321