Project TVA-332 — Project Summary

Queue ID
TVA-332
Capacity
23 MW
Technology
Gas
Status
active
Location
Shelby, TN
Region
Southeast
Developer
IA Status
IA Executed

TVA-332

TVA-332BetaActiveGasTVALBNL

23 MW generation in Shelby, TN · In queue since October 2017 · Proposed COD February 2018

23 MW

Capacity

1

Components

Gas

8y 7m

In Queue

IA Executed

IA Status

COD target: 2018

Interconnection

Total Duration

4 months

Schedule

100 months past proposed COD

Construction75%
Queue EntryOct 18, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2018-02-28

About

TVA-332 is a proposed 23 MW gas-fired generation project located in Shelby County, Tennessee. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of October 18, 2017, and a proposed commercial operation date of February 28, 2018. The point of interconnection is the Allen 161-kV Substation.

The project's interconnection agreement (IA) has been executed.

Generated from interconnection queue and public data sources

Project Details

State

TN

County

Shelby

Grid Region

Southeast

Market

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Service Type

Point of Interconnection

Allen 161-kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
TVA
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.