TVA-332
23 MW generation in Shelby, TN · In queue since October 2017 · Proposed COD February 2018
23 MW
Capacity
1
Components
Gas
8y 7m
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
4 months
Schedule
100 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2018-02-28
TVA-332 is a proposed 23 MW gas-fired generation project located in Shelby County, Tennessee. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of October 18, 2017, and a proposed commercial operation date of February 28, 2018. The point of interconnection is the Allen 161-kV Substation.
The project's interconnection agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
TN
County
Shelby
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Allen 161-kV Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-332