TVA-337
30 MW generation in Lake, TN · In queue since January 2018 · Proposed COD March 2020
30 MW
Capacity
1
Components
Solar
8y 4m
In Queue
IA Executed
IA Status
COD target: 2020
Total Duration
2y 2m
Schedule
75 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2020-03-01
TVA-337 is a proposed 30 MW solar generation project located in Lake County, Tennessee. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of January 2, 2018. The proposed commercial operation date is March 1, 2020, and the interconnection agreement has been executed.
The project, developed by TVA, consists of 30 MW of solar capacity. The point of interconnection is the Highway 412-Tiptonville 161-kV TL. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TN
County
Lake
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Highway 412-Tiptonville 161-kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-337