TVA-341
100 MW generation in Lowndes, MS · In queue since March 2018 · Proposed COD September 2024
100 MW
Capacity
1
Components
Solar
8y 2m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
6y 6m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2024-09-24
TVA-341 is a proposed 100 MW solar generation project located in Lowndes County, Mississippi. The development project is sponsored by the Tennessee Valley Authority (TVA). It consists of 100 MW of solar photovoltaic generation.
The project is currently active in the TVA interconnection queue, with an original queue entry date of March 28, 2018. The proposed commercial operation date is September 24, 2024, and the Interconnection Agreement (IA) has been executed. The point of interconnection is the future Artesia 161-kV Substation.
Generated from interconnection queue and public data sources
State
MS
County
Lowndes
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Artesia 161-kV Substation (future)
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-341