TVA-374
195 MW generation in Lawrence, TN · In queue since June 2019 · Proposed COD June 2028
195 MW
Capacity
1
Components
Solar
6y 11m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
9 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-06-02
TVA-374 is a proposed 195 MW solar generation project located in Lawrence County, Tennessee. The project is being developed within the Tennessee Valley Authority (TVA) service area. It entered the TVA interconnection queue on June 4, 2019, and has a proposed commercial operation date of June 2, 2028. The project's interconnection agreement (IA) has been executed.
The point of interconnection for TVA-374 is planned for the future Iron City, TN 161-kV Substation. Recent news coverage has discussed the development of solar projects in the TVA region.
Generated from interconnection queue and public data sources
State
TN
County
Lawrence
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Iron City, TN 161-kV Substation (future)
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-374