TVA-377
100 MW generation in Lowndes, MS · In queue since June 2019 · Proposed COD September 2024
100 MW
Capacity
1
Components
Solar
6y 11m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
5y 3m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2024-09-24
TVA-377 is a proposed 100 MW solar generation project located in Lowndes County, Mississippi. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of June 11, 2019. The proposed commercial operation date is September 24, 2024, and the interconnection agreement has been executed.
The point of interconnection for the project is the future Artesia 161-kV Substation. The developer is listed as TVA. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
MS
County
Lowndes
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Artesia 161-kV Substation (future)
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-377