TVA-385
200 MW generation in Lawrence, AL · In queue since August 2019 · Proposed COD May 2026
200 MW
Capacity
1
Components
Solar
6y 9m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-05-04
The proposed TVA-385 project is a 200 MW solar generation facility located in Lawrence County, Alabama. The project is being developed within the Tennessee Valley Authority (TVA) service area.
The project entered the TVA interconnection queue on August 1, 2019, and has a proposed commercial operation date of May 4, 2026. The interconnection agreement (IA) for the project has been executed. The point of interconnection is the Trinity - Nance 161-kV TL.
Generated from interconnection queue and public data sources
State
AL
County
Lawrence
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Trinity - Nance 161-kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-385