TVA-405
193 MW generation in Lawrence, AL · In queue since November 2019 · Proposed COD May 2027
193 MW
Capacity
1
Components
Solar
6y 6m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-05-28
TVA-405 is a proposed 193 MW solar generation project located in Lawrence County, Alabama. The development project is in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of November 18, 2019. The project's proposed commercial operation date is May 28, 2027, and its Interconnection Agreement (IA) has been executed.
The project, sponsored by TVA, consists of 193 MW of solar photovoltaic generation. The point of interconnection (POI) is at CR BRK 242 - Mountain Home 161-kV TL. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AL
County
Lawrence
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
CR BRK 242 - Mountain Home 161-kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.